[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388669":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388669,172,1,"单选题","WBS最底层的工作单元被称为工作包，以下关于工作包的叙述中，正确的是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可依据工作包来确定进度安排、成本估算等工作",true,{"key":16,"text":17,"correct":18},"B","工作包可以非常具体，也可以很粗略，视项目情况而定",false,{"key":20,"text":21,"correct":18},"C","如果项目规模很大，也可以将其分解为子项目，这时子项目可以认为是一个工作包",{"key":23,"text":24,"correct":18},"D","工作包的规模应该较小，可以在40小时之内完成","某个可交付成果，如果具有如下特征之一，就可能被当成工作包：① 规模较小，可以在短时间（80小时）完成。② 从逻辑上讲，不能再分了。③ 所需资源、时间、成本等可以比较准确地估算，已经可以对其进行有效的时间、成本、质量、范围和风险控制。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]