[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388668":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388668,172,1,"单选题","项目的需求文档应精准描述要交付的产品，应能反映出项目的变更。当不得不做出变更时，应该 （ ） 对被影响的需求文件进行处理。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","从关注高层系统需求变更的角度",false,{"key":16,"text":17,"correct":14},"B","从关注底层功能需求变更的角度",{"key":19,"text":20,"correct":21},"C","按照从高层到底层的顺序",true,{"key":23,"text":24,"correct":14},"D","按照从底层到高层的顺序","在需求文档中一定要反映项目的变更，需求文档应精确描述要交付的产品。当不得不做出变更时，应该按从高到低的顺序对被影响的需求文档进行处理。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]