[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388667":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388667,172,1,"单选题","在进行项目需求管理时，某需求的状态描述是\"该需求已被分析，估计了其对项目余下部分的影响，已用一个明确的产品版本号或创建编号分配到相关的基线中，软件开发团队已同意实现该需求\"，则这个需求状态值是 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","已建议",false,{"key":16,"text":17,"correct":14},"B","已验证",{"key":19,"text":20,"correct":14},"C","已实现",{"key":22,"text":23,"correct":24},"D","已批准",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]