[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388666":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388666,172,1,"单选题","某项目范围基准发生变化，经 （请作答此空） 同意，对需求规格说明书进行变更，则该配置项的状态应从 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","技术负责人",{"key":19,"text":20,"correct":14},"C","配置管理员",{"key":22,"text":23,"correct":24},"D","变更控制委员会",true,"变更需要经过CCB批准后才能实施，并且配置项的状态由\"正式发布\"变迁为\"正在修改\"。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]