[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388647":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388647,172,1,"单选题","《项目质量管理计划》经评审后进入批准流程。由于项目前期已拖期两周，该文件应尽快报监理审批，那么对于该文件的批准活动，正确的是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由建设方技术总监对内容、范围审核后送交监理方批准",true,{"key":16,"text":17,"correct":18},"B","由承建方项目经理对内容、范围审核后送交监理方批准",false,{"key":20,"text":21,"correct":18},"C","由监理工程师对内容、范围审核后送交总监理工程师批准",{"key":23,"text":24,"correct":18},"D","先和批准人打声招呼，走监理批准流程，事后再补发签字","监理方要对承建单位提交的所有计划进行审批，但之前要经过建设单位的同意。故《项目质量管理计划》应由建设方技术总监对内容、范围审核后送交监理方批准。即A是正确答案。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]