[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388645":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388645,172,1,"单选题","以下关于项目管理计划编制的理解中，正确的是（ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理应组织并主要参与项目管理计划的编制，但不应独立编制",true,{"key":16,"text":17,"correct":18},"B","项目管理计划的编制不能采用迭代的方法",false,{"key":20,"text":21,"correct":18},"C","让项目干系人参与项目计划的编制，增加了沟通成本，应尽量避免",{"key":23,"text":24,"correct":18},"D","项目管理计划不能是概括的，必须是详细、具体的","项目管理计划可以是概要的或详细的，并且可以包含一个或多个辅助计划。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]