[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388635,172,1,"单选题","某系统集成商现正致力于过程改进，打算为过去的项目建立历史档案，现阶段完成该工作的最好方法是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建立项目计划",false,{"key":16,"text":17,"correct":18},"B","总结经验教训",true,{"key":20,"text":21,"correct":14},"C","绘制网络图",{"key":23,"text":24,"correct":14},"D","制定项目状态报告","总结经验教训可以避免未来的错误，并借用过去项目的好经验，从而可以促进未来项目的改进和进步。建立项目计划过程是为本次项目的未来实施阶段提供指南，而绘制网络图则是制定项目计划的进度分计划的前提条件，制定项目状态报告是报告项目绩效的一种方法。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]