[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388625,172,1,"单选题","（ ） 不属于项目监控工作的成果。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度预测",true,{"key":16,"text":17,"correct":18},"B","项目文件更新",false,{"key":20,"text":21,"correct":18},"C","工作绩效报告",{"key":23,"text":24,"correct":18},"D","项目管理计划更新","项目监控工作的成果有：①变更请求；②工作绩效报告；③项目管理计划更新；④项目文件更新。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]