[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388609":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388609,172,1,"单选题","项目经理小李依据当前技术发展趋势和所掌握的技术能否支撑该项目的开发，进行 可行性研究。小李进行的可行性研究属于 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经济可行性分析",false,{"key":16,"text":17,"correct":18},"B","技术可行性分析",true,{"key":20,"text":21,"correct":14},"C","运行环境可行性分析",{"key":23,"text":24,"correct":14},"D","其他方面的可行性分析","从\"依据当前技术发展趋势和所掌握的技术能否支撑该项目的开发\"这句话判断为技术可行性研究。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]