[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388603":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388603,172,1,"单选题","某地方政府准备立项改造一个小型信息系统，由于项目投资额较小，立项过程可以简化，但其中的 （ ） 环节不能缺失。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","信息系统安全风险评估报告的编制和报批",false,{"key":16,"text":17,"correct":14},"B","初步设计方案的编制和报批",{"key":19,"text":20,"correct":21},"C","可行性研究报告的编制和报批",true,{"key":23,"text":24,"correct":14},"D","项目评估","机会研究、初步可行性研究、详细可行性研究、评估与决策是投资前期的四个阶段。在实际工作中，前三个阶段依项目的规模和繁简程度可把前两个阶段省略或合二为一，但详细可行性研究是不可缺少的。升级改造项目只做初步和详细研究，小项目一般只进行详细可行性研究。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]