[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388595,172,1,"单选题","以下关于项目评估的叙述中， （ ） 是正确的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目评估的最终成果是项目评估报告",true,{"key":16,"text":17,"correct":18},"B","项目评估在项目可行性研究之前进行",false,{"key":20,"text":21,"correct":18},"C","项目建议书作为项目评估的唯一依据",{"key":23,"text":24,"correct":18},"D","项目评估可由项目申请者自行完成","项目评估是指通过项目组之外的组织或者个人对项目进行的评估，通常是指在项目的前期和项目完工之后的评估。项目前期的评估主要指的是对项目的可行性的评估；项目完工后评估是指在信息化项目结束后，依据相关的法规、信息化规划报告、合同等，借助科学的措施或手段对信息化项目的水平、效果和影响，投资使用的合同相符性、目标相关性和经济合理性所进行的评估。可见A是正确的。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]