[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388581,172,1,"单选题","自招标文件开始发出之日起至提交投标文件截止之日止，最短不得少于（ ）日",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","15",{"key":19,"text":20,"correct":21},"C","20",true,{"key":23,"text":24,"correct":14},"D","30","自招标文件开始发出之日起至提交投标文件截止之日止，最短不得少于20日",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]