[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388577":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388577,172,1,"单选题","某系统开发项目邀请第三方进行项目评估， （ ） 不是项目评估的依据。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目建议书及其批准文件",false,{"key":16,"text":17,"correct":14},"B","项目可行性研究报告",{"key":19,"text":20,"correct":14},"C","报送单位的申请报告及主管部门的初审意见",{"key":22,"text":23,"correct":24},"D","项目变更管理策略",true,"评估依据包括：项目建议书及其批准文件项目可行性研究报告报送单位的申请报告及主管部门的初审意见有关资源、配件、燃料、水、电、资金等方面的协议文件必需的其他文件和资料",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]