[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388551,172,1,"单选题","结束软件测试工作时，应按照软件配置管理的要求，将（ ）纳入配置管理。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","全部测试工具",false,{"key":16,"text":17,"correct":18},"B","被测试软件",true,{"key":20,"text":21,"correct":14},"C","测试支持软件",{"key":23,"text":24,"correct":14},"D","以上都是","配置管理：应按照软件配置管理的要求，将测试过程中产生的各种工作产品纳入配置管理。由开发组织实施的软件测试，应将测试工作产品纳入软件项目的配置管理;由独立测试组织实施的软件测试，应建立配置管理库，将被测试对象和测试工作产品纳入配置管理。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]