[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388531":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388531,172,1,"单选题","项目集指导委员会的主要责任是保证项目集能够按照计划实现组织的战略目标，围绕这一基本职能就要求项目集指导委员会承担在组织范围内对项目集的成功识别、启动和实现起到具有关键作用的职责。（ ）一般不属于项目集指导委员会的责任。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","保证项目集与组织愿景和目标的一致性",false,{"key":16,"text":17,"correct":14},"B","项目集批准和启动",{"key":19,"text":20,"correct":21},"C","项目集组件管理",true,{"key":23,"text":24,"correct":14},"D","项目集筹资计划审批","项目集目标的实现，以及最重要的收益的交付是通过授权和启动项目集各组件项目及子项目集实现的。因此项目集经理需要建立一套组件项目和子项目集的治理框架，并根据各组件项目的特点对各组件项目经理进行授权。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]