[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388516":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388516,172,1,"单选题","PMI的0PM3模型是一个三维的模型,对其描述错误的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","第一维是成熟度的四个梯级",false,{"key":16,"text":17,"correct":14},"B","第二维是项目管理的十个领域和五个基本过程",{"key":19,"text":20,"correct":21},"C","第二维是项目管理的十个领域",true,{"key":23,"text":24,"correct":14},"D","第三维是组织项目级项目管理的三个版图层。","OPM3是一个三维的模型，第一维是成熟度的四个梯级，第二维是项目管理的十个领域和五个基本过程，第三维是组织项目级项目管理的三个版图层次。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]