[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388506":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388506,172,1,"单选题","下列选项中．属于变更控制委员会主要任务的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","提出变更申请",false,{"key":16,"text":17,"correct":14},"B","评估变更影响",{"key":19,"text":20,"correct":21},"C","评价、审批变更",true,{"key":23,"text":24,"correct":14},"D","实施变更","变更控制委员会（Change Control Board）也称为配置控制委员会，是配置项变更得监管组织，其任务是对建议的配置项变更做出评价、审批以及监督已批准变更的实施。 提出变更申请和评估变更影响是变更申请人的主要工作 实施变更是变更实施者的主要工作。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]