[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388500":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388500,172,1,"单选题","以下有关变更控制方面的描述中，（ ）是正确的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","任何变更都要得到三方（建设单位、监理单位和承建单位）的书面确认，严禁擅自变更。",true,{"key":16,"text":17,"correct":18},"B","承建单位或建设单位是变更的申请者，监理方不能提出变更申请。",false,{"key":20,"text":21,"correct":18},"C","承建单位提出变更申请，一般应首先递交业主初审，同意后再与监理协商确定变更方法。",{"key":23,"text":24,"correct":18},"D","建设单位不能提出变更申请","三方均能申请变更。乙方申请的变更，一般由监理方初审。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]