[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388498":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388498,172,1,"单选题","某项目在执行过程中，软件的需求基线已经确定后，客户需要增加新的功能，但该需求变更会对已经完成系统的稳定性有较大影响。作为项目负责人处理这些需求变更，下列（ ）做法是不合适的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","利用原型法给用户提供预览，以帮助准确把握用户的真实需求",false,{"key":16,"text":17,"correct":14},"B","可以跟客户说不，并与其商议在后续项目或下一版本中满足他们的要求",{"key":19,"text":20,"correct":21},"C","秉承“客户至上”的原则，召集有关人员开始变更工作，满足客户的要求",true,{"key":23,"text":24,"correct":14},"D","利用在项目初期文档化的视图、范围、限制，与变更项比较，决定是否采用此项变更","题干中指出“该需求变更会对已经完成系统的稳定性有较大影响”，因此选项“C．秉承“客户至上”的原则，召集有关人员开始变更工作，满足客户的要求”是不合适的。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]