[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388495":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388495,172,1,"单选题","变更管理有两个重要的用途，一是（ ）；二是变更度量分析，帮助组织提升自身的项目管理能力。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分析变更的原因，并管理这些原因",false,{"key":16,"text":17,"correct":14},"B","规避风险，确保项目顺利",{"key":19,"text":20,"correct":14},"C","限制变更，维持项目的计划",{"key":22,"text":23,"correct":24},"D","控制变更，保证项目可控",true,"BC肯定是不对的，变更是不可避免的，也不能一味的去限制变更。 变更管理要能体现出它的两个重要用途，一个是控制变更，保证项目可控；一个是变更度量分析，帮助组织提供自己的开发能力。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]