[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388450":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388450,172,1,"单选题","某项目在启动阶段难以确定所需要的人员和资源，需要在实施过程中动态增加较多人员、专家和外部资源。在为该项目制订采购计划时需要确定采购合同类型，最适合该项目的合同类型是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时间和材料合同",true,{"key":16,"text":17,"correct":18},"B","成本加固定酬金合同",false,{"key":20,"text":21,"correct":18},"C","成本补偿合同",{"key":23,"text":24,"correct":18},"D","固定总价合同","用于编制采购计划过程的技术、方法：时间和材料合同是包含成本补偿合同和固定总价合同的混合类型。当不能迅速确定准确的工作量时，时间和材料合同适用于动态增加人员、专家或其他外部支持人员等情况",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]