[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388439":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388439,172,1,"单选题","WBS应该被用于风险识别过程，因为它（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定所有要做的工作，因此，能帮助识别潜在的危险源",true,{"key":16,"text":17,"correct":18},"B","确定所有要做的工作，因此，包括项目所有的风险",false,{"key":20,"text":21,"correct":18},"C","帮助组织项目所要完成的所有工作",{"key":23,"text":24,"correct":18},"D","确定工作包，这将使分配特定的责任成为可能","因为WBS确定必须要做的所有工作，它是一个识别潜在风险源的好工具。但是，并非项目中的每个风险都是通过只检查WBS发现的",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]