[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388438":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388438,172,1,"单选题","在风险监控中，如果出现了风险登记单未预期的风险或“观察清单”未包含的风险，应该（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进行额外的风险应对规划",true,{"key":16,"text":17,"correct":18},"B","进行风险审计",false,{"key":20,"text":21,"correct":18},"C","进行变差和趋势分析",{"key":23,"text":24,"correct":18},"D","召开状态审查会","风险再评估。风险监控过程通常要求使用本章介绍的过程对新风险进行识别并对风险进行重新评估。应安排定期进行项目风险再评估。项目团队状态审查会的议程中应包括项目风险管理的内容。重复的内容和详细程度取决于项目相对于目标的进展情况。例如，如果出现了风险登记单未预期的风险或“观察清单”未包括的风险，或其对目标的影响与预期的影响不同，规划的应对措施可能将无济于事，则此时需要进行额外的风险应对规划以对风险进行控制。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]