[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388433":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388433,172,1,"单选题","通过概率和影响级别定义以及专家访谈，有助于纠正该过程所使用的数据中的偏差属于（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定性风险分析",true,{"key":16,"text":17,"correct":18},"B","识别风险",false,{"key":20,"text":21,"correct":18},"C","定量风险分析",{"key":23,"text":24,"correct":18},"D","风险监控","本题考察，定性风险定义。 定性风险分析：对风险概率和影响进行评估和汇总，进而对风险进行排序，以便随后进一步分析或行动。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]