[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388426":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388426,172,1,"单选题","A公司承接了某银行网上银行系统的建设项目，包括应用软件开发、软硬件集配、系统运维等多项工作内容。针对该项目，不正确的是：（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目的干系人包括客户、公司高层领导、项目成员以及网上银行用户",false,{"key":16,"text":17,"correct":18},"B","干系人管理工作应由该项目成员分工负责",true,{"key":20,"text":21,"correct":14},"C","干系人管理有助于为项目赢得更多的资源",{"key":23,"text":24,"correct":14},"D","通常来说，干系人对项目的影响能力在项目启动阶段最大，随着项目的进展逐渐减弱","干系人管理工作应由项目经理负责。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]