[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388385":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388385,172,1,"单选题","基于你的制造项目的质量控制测量，管理层认训到需要立即对材料需求计划（MRP）系统进行纠正，以避免在未来的项目中出现返工问题。为执行必要的变更，你必须遵循（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","机构的质量政策",false,{"key":16,"text":17,"correct":14},"B","质量管理计划",{"key":19,"text":20,"correct":14},"C","已制订的操作定义和程序",{"key":22,"text":23,"correct":24},"D","整体变更控制程序",true,"作为质量控制测量的结果，过程调整由立即纠正和预防行为组成。在有些情况下，这种过程调整应该根据整体变更控制的程序进行处理。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]