[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388374,172,1,"单选题","在项目质量计划编制过程常用的工具和技术中（ ）是将实际实施过程中或计划之中的项目做法同其他类似项目的实际做法进行比较，改善与调高项目的质量。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","成本\u002F效益分析",false,{"key":16,"text":17,"correct":14},"B","试验设计",{"key":19,"text":20,"correct":14},"C","质量成本",{"key":22,"text":23,"correct":24},"D","基准分析",true,"基准分析在项目实际实施过程中或计划做法，以其他类似项目的实际做法作为基准，将二者进行比较，就是基准分析。通过这样的比较来改善与提高目前项目的质量管理，以达到项目预期的质量或其他目标。作为基准的其他项目可以是执行组织内部的项目，也可以是外部的项目，可以是同一个应用领域的项目，也可以是其他应用领域的项目。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]