[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388370":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388370,172,1,"单选题","Estimate Activity Duration sis the process of estimating the number of work period sto complete indivities with estimated resources.The tools and technques is not including（ ）.",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","expert judgment",false,{"key":16,"text":17,"correct":14},"B","analogous estimating",{"key":19,"text":20,"correct":21},"C","requirements trace ability matrix",true,{"key":23,"text":24,"correct":14},"D","three-point estimating","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]