[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388366":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388366,172,1,"单选题","（ ）不属于项目成本预算的输入。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目范围说明书",false,{"key":16,"text":17,"correct":14},"B","工作分解结构",{"key":19,"text":20,"correct":21},"C","项目资金需求",true,{"key":23,"text":24,"correct":14},"D","项目进度计划","A、B、D均是项目成本预算的输入，C是成本预算的输出。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]