[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388365":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388365,172,1,"单选题","小李所负责的项目已经完成了20%。最近一次的挣值分析结果显示，成本绩效指数（CPI）为0.67，进度绩效指数（SPI）为0.87。在这种情况下，小李应该（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实施额外的资源计划编制，增加资源，并且在需要的时候进行超时工作，以完成已预算好的工作量",false,{"key":16,"text":17,"correct":14},"B","为进度重新设定基准，然后使用蒙特卡罗分析",{"key":19,"text":20,"correct":21},"C","实施风险应对审计以帮助控制风险",true,{"key":23,"text":24,"correct":14},"D","更新风险的识别、定性风险分析和定量风险分析","当前CPI及SPI均小于1，说明项目当前成本超支、进度落后。应实施风险应对。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]