[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388364":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388364,172,1,"单选题","在进行挣值管理时，如果实际进度点位于PV曲线的左侧，则该点与PV曲线的垂直距离表示实际进度比计划进度（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","超前的时间",false,{"key":16,"text":17,"correct":14},"B","拖后的时间",{"key":19,"text":20,"correct":21},"C","超额完成的任务量",true,{"key":23,"text":24,"correct":14},"D","拖欠的任务量","PV是计划完成的工作量，在PV的左侧，则表示在检查点处，相同计划量用时比计划时间短，进度超前，则该点与PV曲线的垂直距离表示超额完成的任务量",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]