[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388363":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388363,172,1,"单选题","如果某工作包的工作估算要花费$1500,截至目前已花费了$1350,而仅完成了2\u002F3,那么成本偏差是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","$150",false,{"key":16,"text":17,"correct":14},"B","—$150",{"key":19,"text":20,"correct":21},"C","一$350",true,{"key":23,"text":24,"correct":14},"D","—$500","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]