[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388362":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388362,172,1,"单选题","项目的成本绩效指数是0.82，这意味着你应当（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","重点提高实际进程的及时性",false,{"key":16,"text":17,"correct":14},"B","重新评估产品的生命周期成本，包括生命周期阶段的长度",{"key":19,"text":20,"correct":14},"C","承认你最初的估算存在根本性缺陷，并且项目并不处于常规情况",{"key":22,"text":23,"correct":24},"D","重点提高正执行工作的生产率",true,"成本落后挣值，应该提高工作的生产率。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]