[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388360":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388360,172,1,"单选题","某项目经理已经完成了WBS和每个工作包的成本估算。要根据这些数据编制项目成本估算，该项目经理要（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","使用WBS的最高层次进行类比估算",false,{"key":16,"text":17,"correct":18},"B","计算工作包和风险储备估算的总和",true,{"key":20,"text":21,"correct":14},"C","把工作包估算累计成为项目估算总和",{"key":23,"text":24,"correct":14},"D","获得专家对项目成本总计的意见","成本估算应考虑风险。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]