[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388358":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388358,172,1,"单选题","甲公司生产急需5000个零件，承包给乙工厂进行加工，每个零件的加工费预算为20元，计划2周（每周工作5天）完成。甲公司负责人在开工后第9天早上到乙工厂检查进度，发现己完成加工3600个零件，支付款项81000元。经计算，（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","该项目的费用偏差为-18000元",false,{"key":16,"text":17,"correct":14},"B","该项目的进度偏差为-18000元",{"key":19,"text":20,"correct":14},"C","该项目的CPI为0.80",{"key":22,"text":23,"correct":24},"D","该项目的SPI为0.90",true,"PV=80000EV=72000AC=81000CV=EV-AC=72000-81000=-9000SV=EV-PV=72000-80000=-8000CPI=EV\u002FAV=72000\u002F81000=0.89SPI=EV\u002FPV=72000\u002F80000=0.9",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]