[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388357":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388357,172,1,"单选题","在你的项目中，你需要将成本归于发生成本的期间。为此，你应该（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","识别项目组成成份以分配成本",false,{"key":16,"text":17,"correct":18},"B","在成本预算中考虑项目进度",true,{"key":20,"text":21,"correct":14},"C","准备详细和精确的成本估算",{"key":23,"text":24,"correct":14},"D","准备成本执行计划","项目绩效衡量以来成本和时间表信息。仅仅知道发生一定的成本是不够的。一个项目经理必须同时知道何时该成本应该发生以及什么时候实际发生了该成本。项目时间表包含消耗成本的项目组成成分的计划开始和结束日期。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]