[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388353":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388353,172,1,"单选题","某大型项目进行到两年时，使用挣值法所需的三个中间变量的数值分别是：计划值PV为400万元，实际成本AC为200万元，挣值EV为100万元。基于该项目的成本偏差，下列描述中正确的是（ ）；基于该项目的成本绩效指数，下列描述中正确的是成本绩效指数小于1，且实际发生的成本是预算成本的2倍。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目成本偏差为负，且项目处于超支状态",true,{"key":16,"text":17,"correct":18},"B","项目成本偏差为正，且项目处于超支状态",false,{"key":20,"text":21,"correct":18},"C","项目成本偏差为负，且项目处于成本节约状态",{"key":23,"text":24,"correct":18},"D","项目成本偏差为正，且项目处于成本节约状态","CV=AC–PV=200-400=-200\u003C0，因此成本偏差为负，项目处于超支状态。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]