[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388348":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388348,172,1,"单选题","某信息系统集成项目计划6周完成，项目经理就前4周的项目进展情况进行分析和汇报情况如下，项目的成本执行指数CPI为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.83",true,{"key":16,"text":17,"correct":18},"B","0.87",false,{"key":20,"text":21,"correct":18},"C","0.88",{"key":23,"text":24,"correct":18},"D","0.95","AC=1000+2500+10000+15000=28500元EV=1000*100%+3000*100%+8000*100%+13000*90%=23700元CPI=EV\u002FAC=0.83",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]