[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388346":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388346,172,1,"单选题","在制订进度计划时，已经完成了:①绘制进度网络图;②活动资源估算;③活动历时估算。此时，为了确定各项活动的时差可进行（ ）.",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","资源平衡分析",false,{"key":16,"text":17,"correct":14},"B","进度压缩分析",{"key":19,"text":20,"correct":21},"C","关键路线分析",true,{"key":23,"text":24,"correct":14},"D","假设情景分析","关键路线有零或负值总时差，在关键路线上的计划活动叫做“关键活动”。为了使路线总时差为零或正值，有必要调整活动持续时间、逻辑关系、时间提前与滞后量或其他进度制约因素。一旦路线总时差为零或正值，则还能确定自由时差。自由时差就是在不延误同一网络路线上任何直接后继活动最早开始时间的条件下，计划活动可以推迟的时间长短。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]