[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388344":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388344,172,1,"单选题","资源分析人员在对某项目进行活动资源估算分析时，发现的主要问题是：该项目依赖张工的经验和个人能力，但同时张工还在其它项目中担任重要角色。为了保证项目资源的使用不发生冲突，资源分析人员在进行资源估算时应提交（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","专家评审意见",false,{"key":16,"text":17,"correct":14},"B","活动属性",{"key":19,"text":20,"correct":14},"C","资源类比估算清单",{"key":22,"text":23,"correct":24},"D","活动资源日历",true,"\"活动资源估算的输出是活动资源需求、更新的活动属性、资源分解结构、更新的资源日历和变更请求。因“张工还在其它项目中担任重要角色”，因此源分析人员在进行资源估算时应提交“D．活动资源日历”\"",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]