[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388343":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388343,172,1,"单选题","项目经理对某软件需求分析活动历时估算的结果是：该活动用时2周（假定每周工作时间是5天）。随后对其进行储备分析，确定的增加时间是2天。以下针对该项目储备分析结果的叙述中，（ ）是不正确的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","增加软件需求分析的应急时间是2天",false,{"key":16,"text":17,"correct":14},"B","增加软件需求分析的缓冲时间是该活动历时的20%",{"key":19,"text":20,"correct":14},"C","增加软件需求分析的时间储备是20%",{"key":22,"text":23,"correct":24},"D","增加软件需求分析的历时标准差是2天",true,"项目团队可以在总的项目进度表中以“应急时间”、“时间储备”或“缓冲时间”为名称增加一些时间，这种做法是承认进度风险的表现。在“三点估算”中介绍了“活动历时的均值和方差”计算的方法。活动历时估算所采用的主要方法和技术，没有选项D所说的“历时标准差”这一说法，D的说法是错误的。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]