[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388342":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388342,172,1,"单选题","以下关于关键路径法的叙述，（ ）是不正确的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","如果关键路径中的一个活动延迟，将会影响整个项目计划",false,{"key":16,"text":17,"correct":18},"B","关键路径包括所有项目进度控制点",true,{"key":20,"text":21,"correct":14},"C","如果有两个或两个以上的路径长度一样，就有可能存在多个关键路径",{"key":23,"text":24,"correct":14},"D","关键路径可随项目的进展而改变","项目进度控制点，并非都在关键路径上，也有可能在非关键路径上。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]