[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388341":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388341,172,1,"单选题","项目经理对某软件开发流程中的“概要设计”活动进行历时估算时，参考了以往相关项目活动情况，他采用的是（ ）方法",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专家判断",false,{"key":16,"text":17,"correct":18},"B","类比估算",true,{"key":20,"text":21,"correct":14},"C","参数估算",{"key":23,"text":24,"correct":14},"D","三点估算","参考了以往相关项目得到新项目历时的方法是类比估算。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]