[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388337":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388337,172,1,"单选题","一个新测试中心将在两年内建成。项目发起人和项目经理已经确定并且高层次估算已经开始。预计该项目可以在预算内按进度计划完成。唯一的难点是获得完成工作所需的具有正确专门技能的人力资源。在这种情况下，项目经理应建立（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","风险分析",false,{"key":16,"text":17,"correct":14},"B","责任分配矩阵",{"key":19,"text":20,"correct":14},"C","责任图",{"key":22,"text":23,"correct":24},"D","受资源限制的进度计划",true,"制定进度计划所采用的主要技术和工具中的“资源平衡”。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]