[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388335":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388335,172,1,"单选题","你计划在户外进行项目管理培训课程中有关团队建设的部分。参加者将从事一个游戏以淘汰“最弱的”队员。赢的人将得到公司的达尔文奖。你只能在一年的某些时段安排此活动，因为该活动将在格林兰进行。开始这项活动的最佳时间是7月中旬。当你发展项目计划时，更通用的日期约束之一是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最早开始日期",true,{"key":16,"text":17,"correct":18},"B","固定的最晚开始",false,{"key":20,"text":21,"correct":18},"C","最晚结束日期",{"key":23,"text":24,"correct":18},"D","固定的最早结束","活动开始或结束的强制日期，能用于限制开始或结束的发生，既不早于某个给定的日期又不晚于某个给定的日期。虽然4个日期约束一般都可从项目管理软件中得到，但最早开始日期和最晚结束日期约束更常用。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]