[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388332":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388332,172,1,"单选题","某项目由并行的3个活动甲、乙和丙组成，为活动甲分配3人5天可以完成活动乙分配6人7天可以完成，活动丙分配4人2天可以完成，活动完成后人员可再调配。在此情况下，项目最短工期为（ ）天，此时人员最少配置为10人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":18},"B","7",true,{"key":20,"text":21,"correct":14},"C","8",{"key":23,"text":24,"correct":14},"D","9","最短工期7天，最少配置10人，分配6人去完成乙工作，需要七天，再分配4人去完成丙工作需要2天，完工后，分配3人去完成甲工作。本题考察资源平衡",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]