[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388331":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388331,172,1,"单选题","某项工程的活动明细如下表（时间：周；费用：万元）: 项目总预算由原先的60万元增加到63万元，根据上表，在预算约束下该工程最快能完成时间为（ ）周",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","9",true,{"key":16,"text":17,"correct":18},"B","8",false,{"key":20,"text":21,"correct":18},"C","14",{"key":23,"text":24,"correct":18},"D","12","首先，成本最多63万，超过63万的方案需要排除。画出单代号网络图可知，关键路径是ACD,工期12周，这是在正常进度下。如果全部赶工，关键路径为AB或ACD两条，工期8周，总费用=8+15+17+13+11=64万。超过总成本。如果A不赶工，BCD全部赶工，关键路径为AB或ACD两条，工期9周，总费用=9+10+17+13+11=60万元，符合总成本预算。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]