[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388330,172,1,"单选题","在进度控制中使用假设情景分析的目的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","评审各种情景，使进度与计划保持一致",true,{"key":16,"text":17,"correct":18},"B","记录请求的变更",false,{"key":20,"text":21,"correct":18},"C","针对何时应更新进度基准，提供额外详情",{"key":23,"text":24,"correct":18},"D","更新活动属性","情景假设是假设将来存在一些异常情况，提前假设预知，目的还是使实际进度和计划保持一致。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]