[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388329":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388329,172,1,"单选题","项目进度制定是一个迭代的过程。如果起始和结束的日期不合实际，则项目可能无法按计划完成。因此你认识到进度控制的重要性，你与你的团队一起来定义怎样管理进度变更。你用以下哪种方法记录你的决定（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度变更控制过程",false,{"key":16,"text":17,"correct":18},"B","进度管理计划",true,{"key":20,"text":21,"correct":14},"C","进度风险计划",{"key":23,"text":24,"correct":14},"D","服务水平协议","进度管理计划是整个项目计划的一个辅助因素。它确立了怎样管理进度变更。它可能是正式的也可能性是非正式的、高度细节化的或粗放式或者是基于特殊的项目需要。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]