[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388327":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388327,172,1,"单选题","在进行项目活动历时估算时，如果很难获得项目工作的详细信息，可采用（ ）作为项目活动历时估算的工具。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","参数式估算法",false,{"key":16,"text":17,"correct":18},"B","类比估算法",true,{"key":20,"text":21,"correct":14},"C","预留时间估算法",{"key":23,"text":24,"correct":14},"D","历时的三点估算法","因为不知道项目工作的详细信息，因此无法使用参数估算、预留时间估算法和历时的三点估算法。只可以通过以类似的项目进行估算。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]